The City of Brooklyn Park used a public involvement process to provide all stakeholders in the study area an opportunity to contribute and comment on the project. Upcoming public involvement opportunities and project updates will be posted here as new information becomes available.

2019 - 2020

February 2020

Tree cutting is planned for this week (2/17) in anticipation of construction. These trees need to be cut down prior to nesting periods for certain birds in the area.

Check back to this site as we will make regular updates as actual construction activities begin later this spring.

January 2020

The TH 169/101st Interchange Project is scheduled for construction beginning in spring of 2020. During 2019 the final design of the new interchange was completed and approved along with the needed permitting. Right of way acquisition was also completed in late fall of 2019.

Contractors are preparing their bids to construct the project; the City of Brooklyn Park will open those bids on January 31, 2020 and award the project to the lowest bidder soon thereafter. Construction activities are likely to start in March with initial tree clearing and mobilization of heavy equipment onto the site. The project will be under construction throughout this summer with the new interchange open to traffic in late fall. There will likely be some miscellaneous work which will extend into spring of 2021.

2018

November 2018

The City of Brooklyn Park, in cooperation with its project partners, invites you to an open house meeting for the TH 169/101st Avenue Interchange Project on Thursday, November 29, 2018 at Brooklyn Park City Hall (5200 85th Avenue North) from 5:00 p.m. to 6:30 p.m. This open house serves as an opportunity to review the project layout, learn more about the current project status, and discuss next steps in the project development process. A brief presentation will begin at 5:30 p.m.

May 2018

TThe TH 169/101st Avenue Interchange Project received $4 million in State of Minnesota general obligation bonds.

Thursday, January 4, 2018

The TH 169/101st Avenue Interchange Project received a $1.5 million grant from the Minnesota Department of Employment and Economic Development (DEED) as part of the State’s Transportation Economic Development Infrastructure (TEDI) Program.

Tuesday, January 2, 2018

The TH 169/101st Avenue Interchange Project received a $10 million grant from the Minnesota Department of Transportation (MnDOT) and Department of Employment and Economic Development as part of the State’s Transportation Economic Development (TED) Program.

2017

Wednesday, September 27, 2017

The TH 169/101st Avenue Interchange Project was selected for $7 million in Federal-aid funding through the Regional Solicitation process. The TH 169/101st Avenue Interchange Project is included in the Metropolitan Council’s 2018-2021 Transportation Improvement Program (TIP). Additional information on the 2018-2021 TIP can be found on the Metropolitan Council webpage.

Thursday, March 2, 2017

The Minnesota Department of Transportation (MnDOT) has issued its Findings of Fact and Conclusions (FOF&C) for the TH 169/101st Avenue Interchange Project. Under Minnesota Rules, MnDOT is the responsible governmental unit for the project. MnDOT had determined the proposed TH 169/101st Avenue Interchange Project as described in the EAW and FOF&C does not have the potential for significant environmental impacts. On February 27, 2017, MnDOT concluded that an Environmental Impact Statement (EIS) is not required, and issued a Negative Declaration Order for the project. This concludes the Minnesota state environmental review process for the project.
FOF&C Distribution Memo (PDF)
FOF&C (PDF)

Phase II Study

2016

Tuesday, November 22, 2016

The City of Brooklyn Park, in cooperation with its project partners, held the second open house for Phase II of the TH 169/101st Avenue Interchange Preliminary Design study on November 10th. A preliminary design layout and an Environmental Assessment Worksheet (EAW) have been prepared. This open house served as an opportunity to review and provide input on the layout and EAW, as well as learn more about the next steps including the City of Brooklyn Park’s efforts to obtain funding for the project. This was an informal open house meeting, whereas no formal presentation.

A copy of the boards presented at the Open House can be found on our Documents and Maps page. Your comments are welcome throughout the study – please check out our Contacts page for how to get in touch.

Friday, October 21, 2016

The City of Brooklyn Park, in cooperation with its project partners, invites you to the second open house for Phase II of the TH 169/101st Avenue Interchange Preliminary Design study on November 10th from 5:00-7:00 p.m. at Grace Fellowship Church located at 8601 101st Avenue North in Brooklyn Park. A preliminary design layout and an Environmental Assessment Worksheet (EAW) have been prepared. This open house serves as an opportunity to review and provide input on the layout and EAW, as well as learn more about the next steps including the City of Brooklyn Park’s efforts to obtain funding for the project. This is an informal open house meeting and no formal presentation will be made. Comments received at the meeting will assist the project partners as the project moves forward.
An Environmental Assessment Worksheet (EAW) for the TH 169/101st Avenue Interchange Project has been prepared and is available for public review and comment from October 24 to November 23, 2016. Comments can be mailed, prior to the close of the public comment period, to Rick Dalton, MnDOT Environmental Coordinator, 1500 West County Road B2, Roseville, MN 55113. Comments may also be emailed to richard.dalton@state.mn.us.
EAW Distribution Letter (PDF)
EAW (PDF)
The City of Brooklyn Park recently submitted an application for funding the interchange as part of the Metropolitan Council’s Regional Solicitation process. The process allocates federal transportation funds to locally-initiated projects to meet regional transportation needs. Successful applications will be announced this winter.

2015

Thursday, November 19, 2015

The City of Brooklyn Park, in cooperation with its project partners, held the first open house for Phase 2 of the TH 169/101st Avenue Interchange Preliminary Design study on November 19th from 5:00-7:00 p.m. at Grace Fellowship Church located at 8601 101st Avenue North in Brooklyn Park. The second phase of this project is underway and will include further study and refinement of Alternative #2, which was recommended from the Phase 1 study. As part of the Phase 1 interchange study, a range of system alternatives were developed, evaluated, and scoped for implementation by the study partners. This was an informal open house meeting, whereas no formal presentation.

A copy of the boards presented at the Open House can be found on our Documents and Maps page.

Your comments are welcome throughout the study – please check out our Contacts page for how to get in touch.

Monday, December 01, 2014

The TH 169/101st Avenue Interchange Study is complete (Phase 1). Preliminary Design and environmental documentation for the project is underway (Phase 2).

Phase I Study

2014

Tuesday, September 09, 2014

The City of Brooklyn Park hosted the third Open House for the TH 169/101st Avenue Interchange Study at Brooklyn Park City Hall on Tuesday, September 9, 2014. Attendees had a chance to review, ask questions, and share concerns about the three concept alternatives under consideration. A copy of the boards that were presented at the Open House can be found on our Documents and Maps page.



Your comments are welcome throughout the study – please check out our Contacts page for how to get in touch.

Thursday, September 04, 2014

The City of Brooklyn Park, in cooperation with its project partners, will host an open house at Brooklyn Park City Hall on Tuesday, September 9, from 5:00 – 7:00 p.m. This open house serves as an opportunity to review new information about the project and provide input regarding the three concept alternatives under consideration. The open house meeting will be informal in nature, whereas no formal presentation will be made. Comments received at the meeting will assist the project partners as the project moves forward.

Tuesday, March 25, 2014

The City of Brooklyn Park hosted the second Open House for the TH 169/101st Avenue Interchange Study at Brooklyn Park City Hall on Tuesday, March 25, 2014. Attendees had a chance to review, ask questions, and share concerns about the six concept alternatives under consideration. A copy of the boards that were presented at the Open House can be found on our Documents and Maps page.

Your comments are welcome throughout the study – please check out our Contacts page. for how to get in touch.

Wednesday, February 26, 2014

The City of Brooklyn Park, in cooperation with its project partners, will host an open house at Brooklyn Park City Hall on Tuesday, March 25, from 5:00 – 7:00 p.m. This open house will serve as an opportunity to review new information about the project and provide input regarding the six concept alternatives under consideration. The open house meeting will be informal in nature, whereas no formal presentation will be made. Comments received at the meeting will assist the project partners as the project moves forward.

2013

Thursday, November 14, 2013

The City of Brooklyn Park hosted the first Open House for the TH 169/101st Avenue Interchange Study at Brooklyn Park City Hall on Thursday, November 14, 2013. Attendees had a chance to review, ask questions, and share concerns about current and future transportation issues and development in the study area. A copy of the boards that were presented at the Open House can be found on our Documents and Maps page. Your comments are welcome throughout the study – please check out our Contacts page for how to get in touch.



Friday, November 1, 2013

The City of Brooklyn Park, in cooperation with its project partners, will host an Open House at Brooklyn Park City Hall on Thursday, November 14, from 4:00 – 7:00 p.m. Come learn, share concerns and suggestions on the interchange study at Highway 169 and 101st Avenue as it relates to current and future transportation issues and development in the area.

Thursday, September 19, 2013

The TH 169/101st Avenue Interchange Study has officially begun. Check back for project updates and additional information as it becomes available.